Â
 | Items | Specifications | Remarks |
Material of coil | Material Thickness | 0.4-0.8 mm galvanized sheet G550 | Â |
Forming system | Rolling Speed | About 20 m/min line speed | Â |
Roller Stations | About 9 stations | Â | |
Roller Material | 45# Steel with quenching 60mm shaft  |
 | |
Maim Motor Power | 5.5 kw | Â | |
hydraulic station Power | 4 kw | Â | |
Cutting system |
Material Of Cutting | CR12 with quench treatment | Â |
Hardness | HRC58-62 | Â | |
Tolerance | +-1.5mm | Â | |
Electrical control system | Electric Source | 380V, 50HZ,3 phase Also can satisfy Customer's require |
 |
Control System | PLC control system | Â | |
 | Weight | About 2.5 tons |  |
 | Way Of Drive | 1 inch single chain |  |
 | Size of machine | Length 4500mm* Width 500mm* Height 800m |  |
Transportion
All goods will be shipped to your country, containers number will be decided with how many machines you would choose
Installation of the machine
   The individual components of the machine are installed according to the layout and prepared for the commissioning.
The installation comprises of:
  -  Installation by Suhang service technicians.
   -  The following services are included:
   -  Installation of the machine components.
   -  Adjustment of the machine components.
   -  Connection of all motors to the control cabinet.
   -  Installation of the required safety devices.
   Delivery extent does not comprise of:
   - Media supply (electrics, compressed air, etc.)to the machine(control cabinet)
   - Raw material,process material and fuels
   - Raw material for test blocks
   - Transport and lifting devices
-Â Auxiliary staff.
   The operators of the plant should be present during the installation in order to become familiar with the new machines.
Commissioning of the machine
   The components of the machine are commissioned one after the other. At the end of the commissioning the machine is ready for production and is handed over.
   The commissioning comprises:
   - Commissioning by Suhang service technicians
   - Training at the machine
   - The following services are rendered
   - Run up of the machine components
   - Testing of all functions of the machine components
   - Start of a fully automatic molding process
   - Execution of machine acceptance
   Delivery extent does not comprise of:
   - Raw materials, process materials and consumables
   - Raw material for test blocks
   - Transport and lifting devices
   The operators of the plant should be present during the commissioning in order to become familiar with the new machines.
Our After-Sales Service Commitments
   Suhang hereby solemnly promises: We implement the "three guarantees" service policy for any equipments sold by Suhang, provide free of charge installation guidelines, commissioning and maintenance of the equipments, training of the Buyer's relevant Operators; and provide technical requirements for the installation and operation of the equipments, technical layout diagrams and other related information, provide a lifetime supply of maintenance and spare parts
The detailed measures are as follows:
1. Guidelines for installation and commissioning of equipments:
Based on the actual situation, to assist and guide the Buyer and Buyer's technical personnel in the overall installation location, the installation of equipments, and provide Buyer with answers to their questions and related issues;
2. Provide training for operation and maintenance personnel:
Based on the Buyer's request, Suhang will provide free of charge training of the operation and maintenance personnel;
a) The User (Buyer) can send their operation and maintenance personnel to our factory for learning and training;
b) When Suhang is doing the installation and test running of the equipments for the Buyer, the Buyer can send their personnel to participate.
3. If failure occurs in any of the machines during the "three guarantees" period(one year), then, upon the Buyer's request, Suhang will eliminate the failure;
4. Suhang will inform all its Buyers about any upgrades and significant product improvements. Suhang will provide equipment modifications based on their costs. Suhang will provide Buyers with high-quality after-sales services in a careful and responsible attitudes, provide very strong guarantee for the Buyer's normal production.
We provide quick and satisfactory customer service, and promise to respond within 24 hours after receiving your complaints by phone or email.
Commercial conditions
Â
Payment terms:
40 % deposit, then T/T 60% after the inspection of the equipments by the Buyer or the Buyer's representative at the Seller's factory, but before shipment;
Delivery time:Â 45 days after received the payment
Warranty Period:
12 months warranty period, starting from the date of the successful installation and commissioning of the equipments at the Buyer's Installation site.
JD series of scheduling winch for flameproof for mine underground or ground load scheduling marshalling harvesters and roadway checked harvesters and other auxiliary handling in the middle. Winch using planetary gear transmission, winch has a compact structure, good rigidity, high efficiency, easy installation and moving, smooth starting, flexible operation, reliable braking, low noise characteristics.
JD series of scheduling winch is composed of motor, drum devices, brakes or hydraulic push rod, the base and cover parts.
JD series of scheduling winch by operating brake and working brake winch drum forward and stops, so as to realize the weight of the traction and stop the two kinds of working condition. In each winch in the design of the internal parts adopt rolling bearing, flexible operation.
JD-1.6 Underground Mining Dispatching Winch Manufacturer, JD-1.6 Underground Mining Dispatching Winch Manufacturer, JD-1.6 Underground Mining Dispatching Winch Manufacturer
Mining Machine,Pulling Electric Winch,Mining Separation Machine,Mining Rig Machine,Mining Equipment
Shandong Hightop Machinery Co,.Ltd , https://www.hightopmachinery.com